[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-437626":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},437626,203,1,"单选题","下列关于AOE网的叙述中，不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键活动不按期完成就会影响整个工程的完成时间",false,{"key":16,"text":17,"correct":18},"B","任何一个关键活动提前完成。那么整个工程将会提前完成",true,{"key":20,"text":21,"correct":14},"C","所有的关键活动提前完成，那么整个工程将会提前完成",{"key":23,"text":24,"correct":14},"D","某些关键活动提前完成，那么整个工程将会提前完成","关键路径是指从有向图的源点到汇点的最长路径。某些关键活动提前完成，那么整个工程将会提前完成，但不是任何一个关键活动提前完成，就能保证整个工程将会提前完咸。",{"id":6,"name":27,"category":28,"favorite":29},"计算机 (电网)","公务员",0]