[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-437468":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},437468,203,1,"单选题","下面关于工程计划的AOE网的叙述中，不正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","某些关键活动若提前完成，那么整个工程将会提前完",false,{"key":16,"text":17,"correct":14},"B","关键活动不按期完成就会影响整个工程的完成时间",{"key":19,"text":20,"correct":21},"C","任何一个关键活动提前完成，那么整个工程将会提前完成",true,{"key":23,"text":24,"correct":14},"D","所有的关键活动都提前完成，那么整个工程将会提前完成","AOE网中的关键路径可能不止一条，如果某一个关键活动提前完成，还不能提前整个工程，则必须同时提高在几条关键路径上的关键活动。",{"id":6,"name":27,"category":28,"favorite":29},"计算机 (电网)","公务员",0]