[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-437446":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},437446,203,1,"单选题","关键路径是AOE网中()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","最长的回路",false,{"key":16,"text":17,"correct":14},"B","最短的回路",{"key":19,"text":20,"correct":21},"C","从源点到终点的最长路径",true,{"key":23,"text":24,"correct":14},"D","从源点到终点的最短路径","关键路径是指从开始顶点到结束顶点的最短路径，路径的长度也是工程完成的最少时间。关键活动是指关键路径上的所有活动，关键活动的最大特征是该活动的最早开始时间等于该活动所允许的最迟开始时间。",{"id":6,"name":27,"category":28,"favorite":29},"计算机 (电网)","公务员",0]