[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-437350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},437350,203,1,"单选题","在AOE网络中关键路径叙述正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","从开始顶点到完成顶点的具有最大长度的路径，关键路径长度是完成整个工程所需的最短时间",true,{"key":16,"text":17,"correct":18},"B","从开始顶点到完成顶点的具有最小长度的路径，关键路径长度是完成整个工程所需的最短时间",false,{"key":20,"text":21,"correct":18},"C","从开始顶点到完成顶点的具有最大长度的路径，关键路径长度是完成整个工程所需的最长时间",{"key":23,"text":24,"correct":18},"D","从开始顶点到完成顶点的具有最小长度的路径，关键路径长度是完成整个工程所需的最长时间","关键路径是指从有向图的源点到汇点的最长路径。某些关键活动提前完成，那么整个工程将会提前完成，但不是任何一个关键活动提前完成，就能保证整个工程将会提前完成。",{"id":6,"name":27,"category":28,"favorite":29},"计算机 (电网)","公务员",0]