[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-432723":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},432723,202,1,"单选题","图所示结构用位移法计算时最少的未知数为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","利用位移法计算，水平杆右端刚结点有一个线位移一个角位移，左端线位移和右边刚节点的线位移是一致的可不作为基本未知量。所以有两个独立的未知量。",{"id":6,"name":27,"category":28,"favorite":29},"机械动力类 (电网)","公务员",0]