[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-429762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},429762,200,1,"单选题","在网络计划技术中，进行时间与成本优化时，一般地说，随着施工周期的缩短，直接费用是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","降低的",false,{"key":16,"text":17,"correct":14},"B","不增不减的",{"key":19,"text":20,"correct":21},"C","增加的",true,{"key":23,"text":24,"correct":14},"D","难以估计的","",{"id":6,"name":27,"category":28,"favorite":29},"管理科学与工程类 (电网)","公务员",0]