[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-429726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},429726,200,1,"单选题","在箭线式网络固中，（ ）的说法是错误的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","结点不占用时间也不消耗资源",false,{"key":16,"text":17,"correct":14},"B","结点表示前接活动的完成和后续活动的开始",{"key":19,"text":20,"correct":14},"C","箭线代表活动",{"key":22,"text":23,"correct":24},"D","结点的最早出现时间和最迟出现时间是同一个时间",true,"",{"id":6,"name":27,"category":28,"favorite":29},"管理科学与工程类 (电网)","公务员",0]