[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-427444":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},427444,199,1,"单选题","某部队计划为驻地村民修3600米水渠，实际工作效率是原计划的1.8倍，结果提前20天修完，原计划每天修：( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","180米",false,{"key":16,"text":17,"correct":14},"B","144米",{"key":19,"text":20,"correct":21},"C","80米",true,{"key":23,"text":24,"correct":14},"D","72米","计划与实际工作效率之比为1：1.8，则工作时间之比为1.8：1。因此实际工作时间为20÷0.8=25天，原计划修20+25=45天，每天修3600÷45=80米。",{"id":6,"name":27,"category":28,"favorite":29},"公共与行业知识 (电网)","公务员",0]