[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-427384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},427384,199,1,"单选题","筑路队原计划每天筑路720米，实际每天比原计划多筑路80米，这样在规定完成全路修筑任务的前3天，就只剩下1160米未完成，这条路全长多少千米？( )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","8.10",false,{"key":16,"text":17,"correct":14},"B","10.12",{"key":19,"text":20,"correct":21},"C","11.16",true,{"key":23,"text":24,"correct":14},"D","13.50","现在每天筑路720+80=800(米)，规定时间内，多筑的路是(720+80)×3-1160=2400-1160=1240(米)。规定的时间是1240÷80=15.5(天)，这条路的全长是720×15.5=11160(米)。故本题选C。",{"id":6,"name":27,"category":28,"favorite":29},"公共与行业知识 (电网)","公务员",0]