[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-423381":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},423381,198,1,"单选题","甲公司承建乙公司的一栋商品楼，施工期间甲公司的下列行为不符合法律规定的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","乙公司未按照约定的时间和要求提供场地，甲公司要求顺延工程日期",false,{"key":16,"text":17,"correct":14},"B","经乙公司同意，甲公司将自己承包的部分工作交由第三人完成",{"key":19,"text":20,"correct":21},"C","甲公司允许分包单位将其承包的工程再分包",true,{"key":23,"text":24,"correct":14},"D","因发包人变更计划，甲公司要求增付返工费用","禁止分包单位将其承包的工程再分包。",{"id":6,"name":27,"category":28,"favorite":29},"法学类 (电网)","公务员",0]