[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-423303":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},423303,198,1,"单选题","某省政府批准一大型基础建设项目，须占用耕地外的农田30公顷，关于审批手续。下列说法正确的是：( ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向国务院办理农用地转用审批手续，同时办理土地征收审批手续",true,{"key":16,"text":17,"correct":18},"B","向国务院办理农用地转用审批手续，向省级政府办理土地征收手续",false,{"key":20,"text":21,"correct":18},"C","向省级政府办理农用地转用审批手续，向国务院办理土地征收手续",{"key":23,"text":24,"correct":18},"D","向省级政府办理农用地转用审批手续，同时办理土地征收审批手续","考查占用农田的审批手续。法律依据为《土地管理法》第44条、第45条可知，A选项正确。征收农用地，应先办理农地转用审批，经国务院批准农地转用的，同时办理征地审批手续。",{"id":6,"name":27,"category":28,"favorite":29},"法学类 (电网)","公务员",0]