[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-421642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},421642,197,1,"单选题","220 KV降为110 KV的降压变压器，两侧均与线路相连，则变比为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","220\u002F110",false,{"key":16,"text":17,"correct":14},"B","242\u002F110",{"key":19,"text":20,"correct":21},"C","220\u002F121",true,{"key":23,"text":24,"correct":14},"D","242\u002F121","变压器一次侧绕组的额定电压等于线路额定电压，为220 KV，而二次侧绕组的额定电压为线路额定电压的1.1倍，因此为121 KV，所以变比为220\u002F121。",{"id":6,"name":27,"category":28,"favorite":29},"电工类 (电网)","公务员",0]