[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-421183":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},421183,197,1,"单选题","在电力系统内，由于操作失误或故障发生之后，在系统某些部分形成自振回路，当自振频率与电网频率满足一定关系而发生谐振时，引起的过电压持续时间（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","较短",false,{"key":16,"text":17,"correct":18},"B","较长",true,{"key":20,"text":21,"correct":14},"C","有很长周期性",{"key":23,"text":24,"correct":14},"D","不变","",{"id":6,"name":27,"category":28,"favorite":29},"电工类 (电网)","公务员",0]