[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-419851":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},419851,196,1,"单选题","甲公司在2012年3月与乙客户签订了一份为期12个月的建造合同，约定合同价格为120万元，预计建造成本为100万元。合同规定乙客户将分期支付合同价款，每笔40万元，其中，第一笔在合同签订日支付，第二笔在6个月后支付，最后一笔在建筑物交付使用时支付。在2012年年末，发生成本为65万元。假设所有的成本均为现金流出，情况与预期一致，不考虑相关税费，则甲公司对该建造合同如按完工百分比法计算，应在2012年确认的合同毛利为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","13",true,{"key":20,"text":21,"correct":14},"C","15",{"key":23,"text":24,"correct":14},"D","20","2012年年末完工百分比=65\u002F100×100%=65%，2012年确认的合同毛利=(120-100)×65%=13(万元)。",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]