[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-419594":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},419594,196,1,"单选题","甲公司于2012年10月1日与丙公司签订合同，为丙公司订制一项软件，工期为5个月，合同总收入1000000元。至2012年12月31日，甲公司已发生成本500000元(假定均为开发人员薪酬)，预收账款5000000元。甲公司预计开发该软件还将发生成本600000元。2012年12月31日，经专业测量师测量，该软件的完工进度为45%。2012年确认的劳务收入为()元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","450000",true,{"key":16,"text":17,"correct":18},"B","500000",false,{"key":20,"text":21,"correct":18},"C","1000000",{"key":23,"text":24,"correct":18},"D","454545","2012年确认的劳务收入=1000000×45%=450000(元)。",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]