[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-419237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},419237,196,1,"单选题","在各月在产品数量变动较大的情况下，采用在产品按定额成本计价法将生产费用在完工产品和在产品之间进行分配时，可能导致()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","月末在产品成本为负数",false,{"key":16,"text":17,"correct":14},"B","月初在产品成本为负数",{"key":19,"text":20,"correct":21},"C","本月完工产品成本为负数",true,{"key":23,"text":24,"correct":14},"D","本月发生的生产费用为负数","完工产品成本=月初在产品成本+本月投入的成本-月末在产品成本，由于月末在产品成本是定额计价法，有可能价格过高，会导致完工产品为负数。",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]