[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-418971":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},418971,196,1,"单选题","下列关于产品单位成本的各主要项目的分析公式中，表达不正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","材料消耗量变动的影响= (实际数量-计划数量) x计划价格",false,{"key":16,"text":17,"correct":18},"B","材料价格变动的影响= (实际价格计划价格) X计划数量",true,{"key":20,"text":21,"correct":14},"C","单位产品所耗工时变动的影响= (实际工时-计划工时) X计划每小时工资成本",{"key":23,"text":24,"correct":14},"D","每小时工资成本变动的影响= (实际每小时工资成本-计划每小时工资成本) x实际工时","",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]