[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-418964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},418964,196,1,"单选题","关于工程项目的下列说法中错误的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","《企业内部控制应用指引第11号——工程项目》所称工程项目，是指企业自行或者委托其他单位所进行的建造、安装工程",false,{"key":16,"text":17,"correct":18},"B","《企业内部控制应用指引第11号——工程项目》所称工程项目，不包括委托其他单位所进行的建造、安装工程",true,{"key":20,"text":21,"correct":14},"C","工程造价信息不对称，技术方案不落实，概预算脱离实际，可能导致项目投资失控",{"key":23,"text":24,"correct":14},"D","工程物资质次价高，工程监理不到位。项目资金不落实，可能导致工程质量低劣，进度延迟或中断","",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]