[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-418766":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},418766,196,1,"单选题","工程项目管理中的主要风险不包括( ) 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","立项缺乏可行性研究或者可行性研究流于形式、决策不当、盲目上马，可能导致难以实现预期效益或项目失败",false,{"key":16,"text":17,"correct":14},"B","项目招标暗箱操作，存在商业贿赂，可能导致中标人实质上难以承担工程项目、中标价格失实及相关人员涉案",{"key":19,"text":20,"correct":21},"C","研究成果转化应用不足、保护措施不力，可能导致企业利益受损",true,{"key":23,"text":24,"correct":14},"D","工程物资质次价高、工程监理不到位、项目资金不落实，可能导致工程质量低劣，进度延迟或中断","",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]