[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-417741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},417741,196,1,"单选题","下列有采购业务请购商品与劳务相关控制活动说法中，不恰当的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","生产部门等根据采购计划、对需要购买的已列入存货清单的原材料等项目填写请购单",false,{"key":16,"text":17,"correct":14},"B","生产部门通常在现有库存达到再订购点时就可直接提出采购申请",{"key":19,"text":20,"correct":14},"C","企业内不少部门都可以填列请购单，可以分部门设置请购单的连续编号，每张请购单必须经过对这类支出预算负责的主管人员签字批准",{"key":22,"text":23,"correct":24},"D","编制连续编号的请购单该控制活动，仅与采购交易“完整性”认定相关",true,"选项D不恰当，请购单是证明有关采购交易的“发生”认定的凭据之一，也是采购交易轨迹的起点。",{"id":6,"name":27,"category":28,"favorite":29},"财务会计类 (电网)","公务员",0]