[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-416356":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},416356,195,1,"单选题","某项工程计划300天完工，开工100天后，由于施工人员减少，工作效率下降了20%，问完成该项工程比原计划推迟了多少天？（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","40",false,{"key":16,"text":17,"correct":18},"B","50",true,{"key":20,"text":21,"correct":14},"C","60",{"key":23,"text":24,"correct":14},"D","70","釆用赋值法。设总工作量为300，则开始的效率为1，后来的效率为0.8，先开工100 天，则完成100个工作量，剩下200个工作量，效率为0.8，需要250天，则总共需要100 + 250 = 350天，所以晚了50天。故答案为B。",{"id":6,"name":27,"category":28,"favorite":29},"政法干警","公务员",5]