[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-412555":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},412555,192,1,"单选题","各类模板拆除的顺序和方法，应根据模板设计的规定进行：一般现浇楼盖及框架结构正确的拆模顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拆楼板底模—拆梁侧模—拆梁底模—拆柱模斜撑与柱箍—拆柱侧模",false,{"key":16,"text":17,"correct":14},"B","拆柱侧模—拆柱模斜撑与柱箍—拆楼板底模—拆梁侧模—拆梁底模",{"key":19,"text":20,"correct":21},"C","拆柱模斜撑与柱箍—拆柱侧模—拆楼板底模—拆梁侧模—拆梁底模",true,{"key":23,"text":24,"correct":14},"D","拆柱模斜撑与柱箍—拆柱侧模—拆梁侧模—拆梁底模—拆楼板底模","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产技术基础","职业资格",0]