[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-412115":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},412115,192,1,"单选题","为保障施工作业人员安全，确保工程实体质量，梁、板模板拆除应遵照一定的顺序进行，下列关于梁、板模板拆除顺序的说法中，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先拆梁侧模，再拆板底模，最后拆除梁底模",false,{"key":16,"text":17,"correct":18},"B","先拆板底模，在拆梁侧模，最后拆除梁底模",true,{"key":20,"text":21,"correct":14},"C","先拆梁侧模，在拆梁底模，最后拆除板底模",{"key":23,"text":24,"correct":14},"D","先拆梁底模，在拆梁侧模，最后拆除板底模","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产技术基础","职业资格",0]