[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-411633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},411633,191,1,"单选题","进行建设项目安全预评价依据的设计文件是项目（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可行性研究报告",true,{"key":16,"text":17,"correct":18},"B","建议书",false,{"key":20,"text":21,"correct":18},"C","施工图设计",{"key":23,"text":24,"correct":18},"D","设计说明书","",{"id":6,"name":27,"category":28,"favorite":29},"安全生产管理","职业资格",0]