[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-410311":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},410311,190,2,"多选题","某建设单位的下述做法中，违反了《建设工程安全生产管理条例》所规定的安全责任的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位向施工单位提供了施工现场及毗邻区域内地下管线及其他有关的完整资料",false,{"key":16,"text":17,"correct":18},"B","及时通知了施工单位将合同约定的工期压缩一个月的决定",true,{"key":20,"text":21,"correct":14},"C","在编制工程概算时，确定了建设工程安全作业环境及安全施工措施所需费用",{"key":23,"text":24,"correct":18},"D","将拆除工程分包给了具有相应资质等级的施工单位，并在作出翌日进行拆除工程施工的决定的当天，将有关资料报送主管部门",{"key":26,"text":27,"correct":14},"E","实行施工总承包的建设工程，由总承包单位负责上报事故","BD","",{"id":6,"name":31,"category":32,"favorite":33},"安全生产法律知识","职业资格",0]