[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-172-4":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":621},{"id":5,"name":6,"category":7,"favorite":8},172,"(高级)信息系统项目管理师","职业资格",0,4,50,1856,[13,34,46,58,70,82,94,106,118,130,142,154,166,178,190,202,214,226,238,250,262,274,286,298,310,322,334,346,358,370,382,394,406,418,430,442,453,465,477,489,501,513,525,537,549,561,573,585,597,609],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":24,"analysis":33},388356,1,"单选题","你受雇于一个政府机构来管理一具为期3年、预算达300万美元的项目。如果项目有变更需求，人就需要在每个财政年度的年底有更多的资金注入。你可以在你的项目中使用这些资金。你决定要建立一个成本变更控制系统，这样做的目的是（ ）",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","明确什么时候向项目添加应急资金",false,{"key":24,"text":25,"correct":26},"B","明确定义变更成本基线的程序",true,{"key":28,"text":29,"correct":22},"C","判断成本变动发生的原因",{"key":31,"text":32,"correct":22},"D","判断是否需要修改预算","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":24,"analysis":33},388357,"在你的项目中，你需要将成本归于发生成本的期间。为此，你应该（ ）",[38,40,42,44],{"key":20,"text":39,"correct":22},"识别项目组成成份以分配成本",{"key":24,"text":41,"correct":26},"在成本预算中考虑项目进度",{"key":28,"text":43,"correct":22},"准备详细和精确的成本估算",{"key":31,"text":45,"correct":22},"准备成本执行计划",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},388358,"甲公司生产急需5000个零件，承包给乙工厂进行加工，每个零件的加工费预算为20元，计划2周（每周工作5天）完成。甲公司负责人在开工后第9天早上到乙工厂检查进度，发现己完成加工3600个零件，支付款项81000元。经计算，（ ）。",[50,52,54,56],{"key":20,"text":51,"correct":22},"该项目的费用偏差为-18000元",{"key":24,"text":53,"correct":22},"该项目的进度偏差为-18000元",{"key":28,"text":55,"correct":22},"该项目的CPI为0.80",{"key":31,"text":57,"correct":26},"该项目的SPI为0.90",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":28,"analysis":33},388359,"以下各项中，不能作为项目成本预算工具或技术的是（ ）。",[62,64,66,68],{"key":20,"text":63,"correct":22},"参数估算",{"key":24,"text":65,"correct":22},"资金限制平衡",{"key":28,"text":67,"correct":26},"挣值分析",{"key":31,"text":69,"correct":22},"准备金分析",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},388360,"某项目经理已经完成了WBS和每个工作包的成本估算。要根据这些数据编制项目成本估算，该项目经理要（ ）。",[74,76,78,80],{"key":20,"text":75,"correct":22},"使用WBS的最高层次进行类比估算",{"key":24,"text":77,"correct":26},"计算工作包和风险储备估算的总和",{"key":28,"text":79,"correct":22},"把工作包估算累计成为项目估算总和",{"key":31,"text":81,"correct":22},"获得专家对项目成本总计的意见",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":28,"analysis":33},388361,"进度绩效指数用比率来表示的原因是要（ ）",[86,88,90,92],{"key":20,"text":87,"correct":22},"在不考虑进度偏差价值的情况下，使相关人员能够进行详细的进度分析",{"key":24,"text":89,"correct":22},"区分关键路径和非关键路径工作包",{"key":28,"text":91,"correct":26},"提供了显示某特定时期绩效的可能，该绩效用于趋势分析",{"key":31,"text":93,"correct":22},"测量完成项目所需的实际时间",{"id":95,"libraryId":5,"type":15,"typeLabel":16,"stem":96,"options":97,"answer":31,"analysis":33},388362,"项目的成本绩效指数是0.82，这意味着你应当（ ）。",[98,100,102,104],{"key":20,"text":99,"correct":22},"重点提高实际进程的及时性",{"key":24,"text":101,"correct":22},"重新评估产品的生命周期成本，包括生命周期阶段的长度",{"key":28,"text":103,"correct":22},"承认你最初的估算存在根本性缺陷，并且项目并不处于常规情况",{"key":31,"text":105,"correct":26},"重点提高正执行工作的生产率",{"id":107,"libraryId":5,"type":15,"typeLabel":16,"stem":108,"options":109,"answer":28,"analysis":33},388363,"如果某工作包的工作估算要花费$1500,截至目前已花费了$1350,而仅完成了2\u002F3,那么成本偏差是（ ）",[110,112,114,116],{"key":20,"text":111,"correct":22},"$150",{"key":24,"text":113,"correct":22},"—$150",{"key":28,"text":115,"correct":26},"一$350",{"key":31,"text":117,"correct":22},"—$500",{"id":119,"libraryId":5,"type":15,"typeLabel":16,"stem":120,"options":121,"answer":28,"analysis":33},388364,"在进行挣值管理时，如果实际进度点位于PV曲线的左侧，则该点与PV曲线的垂直距离表示实际进度比计划进度（ ）",[122,124,126,128],{"key":20,"text":123,"correct":22},"超前的时间",{"key":24,"text":125,"correct":22},"拖后的时间",{"key":28,"text":127,"correct":26},"超额完成的任务量",{"key":31,"text":129,"correct":22},"拖欠的任务量",{"id":131,"libraryId":5,"type":15,"typeLabel":16,"stem":132,"options":133,"answer":28,"analysis":33},388365,"小李所负责的项目已经完成了20%。最近一次的挣值分析结果显示，成本绩效指数（CPI）为0.67，进度绩效指数（SPI）为0.87。在这种情况下，小李应该（ ）",[134,136,138,140],{"key":20,"text":135,"correct":22},"实施额外的资源计划编制，增加资源，并且在需要的时候进行超时工作，以完成已预算好的工作量",{"key":24,"text":137,"correct":22},"为进度重新设定基准，然后使用蒙特卡罗分析",{"key":28,"text":139,"correct":26},"实施风险应对审计以帮助控制风险",{"key":31,"text":141,"correct":22},"更新风险的识别、定性风险分析和定量风险分析",{"id":143,"libraryId":5,"type":15,"typeLabel":16,"stem":144,"options":145,"answer":28,"analysis":33},388366,"（ ）不属于项目成本预算的输入。",[146,148,150,152],{"key":20,"text":147,"correct":22},"项目范围说明书",{"key":24,"text":149,"correct":22},"工作分解结构",{"key":28,"text":151,"correct":26},"项目资金需求",{"key":31,"text":153,"correct":22},"项目进度计划",{"id":155,"libraryId":5,"type":15,"typeLabel":16,"stem":156,"options":157,"answer":28,"analysis":33},388367,"在（ ）情况下，可使用储备金。",[158,160,162,164],{"key":20,"text":159,"correct":22},"需要添加额外资金以弥补初始预算",{"key":24,"text":161,"correct":22},"当协商劳动合同时，潜在劳动力价格会发生波动",{"key":28,"text":163,"correct":26},"确定发生了预计的问题但没有估计完全",{"key":31,"text":165,"correct":22},"当客户要求项目高质量完成时",{"id":167,"libraryId":5,"type":15,"typeLabel":16,"stem":168,"options":169,"answer":20,"analysis":33},388368,"每次你与你的项目发起人会面，她都要强调对于你的新的电子商务项目的成本控制的必要性。她经常询问你成本业绩方面的问题，诸如哪一个预算达到了哪一个没有达到。为了回答她的问题，你应该提供（ ）",[170,172,174,176],{"key":20,"text":171,"correct":26},"业绩报告",{"key":24,"text":173,"correct":22},"业绩衡量图表",{"key":28,"text":175,"correct":22},"资源生产力分析",{"key":31,"text":177,"correct":22},"趋势分析统计",{"id":179,"libraryId":5,"type":15,"typeLabel":16,"stem":180,"options":181,"answer":31,"analysis":33},388369,"（ ）不属于成本管理过程",[182,184,186,188],{"key":20,"text":183,"correct":22},"资源计划过程",{"key":24,"text":185,"correct":22},"成本估计过程",{"key":28,"text":187,"correct":22},"成本预算过程",{"key":31,"text":189,"correct":26},"合同评审过程",{"id":191,"libraryId":5,"type":15,"typeLabel":16,"stem":192,"options":193,"answer":28,"analysis":33},388370,"Estimate Activity Duration sis the process of estimating the number of work period sto complete indivities with estimated resources.The tools and technques is not including（ ）.",[194,196,198,200],{"key":20,"text":195,"correct":22},"expert judgment",{"key":24,"text":197,"correct":22},"analogous estimating",{"key":28,"text":199,"correct":26},"requirements trace ability matrix",{"key":31,"text":201,"correct":22},"three-point estimating",{"id":203,"libraryId":5,"type":15,"typeLabel":16,"stem":204,"options":205,"answer":31,"analysis":33},388371,"项目进行到某阶段时，项目经理进行了绩效分析，计算出CPI值为0.91。这表示（ ）。",[206,208,210,212],{"key":20,"text":207,"correct":22},"项目的每91元人民币投资中可创造相当于100元的价值",{"key":24,"text":209,"correct":22},"当项目完成时将会花费投资额的91％",{"key":28,"text":211,"correct":22},"项目仅进展到计划进度的91％",{"key":31,"text":213,"correct":26},"项目的每100元人民币投资中只创造相当于91元的价值",{"id":215,"libraryId":5,"type":15,"typeLabel":16,"stem":216,"options":217,"answer":28,"analysis":33},388372,"项目计划工期为4年，预算总成本为800万元。在项目的实施过程中，通过对成本的核算和有关成本与进度的记录得知，开工后第2年末实际成本发生额为200万元，所完成工作的计划预算成本额为100万元。与项目预算成本比较可知：当工期过半时，项目的计划成本发生额应该为400万元。此时如果不采取任何纠正措施，照此速度发展下去，那么到开工后第4年末项目会出现（ ）万元的成本超支。",[218,220,222,224],{"key":20,"text":219,"correct":22},"50",{"key":24,"text":221,"correct":22},"100",{"key":28,"text":223,"correct":26},"200",{"key":31,"text":225,"correct":22},"400",{"id":227,"libraryId":5,"type":15,"typeLabel":16,"stem":228,"options":229,"answer":28,"analysis":33},388373,"6σ代表以6个标准偏差设立偏差极限目标，而一个过程的正常期望偏差是（ ）",[230,232,234,236],{"key":20,"text":231,"correct":22},"1个标准偏差",{"key":24,"text":233,"correct":22},"2个标准偏差",{"key":28,"text":235,"correct":26},"3个标准偏差",{"key":31,"text":237,"correct":22},"因为每个过程的惟一性而不能确定",{"id":239,"libraryId":5,"type":15,"typeLabel":16,"stem":240,"options":241,"answer":31,"analysis":33},388374,"在项目质量计划编制过程常用的工具和技术中（ ）是将实际实施过程中或计划之中的项目做法同其他类似项目的实际做法进行比较，改善与调高项目的质量。",[242,244,246,248],{"key":20,"text":243,"correct":22},"成本\u002F效益分析",{"key":24,"text":245,"correct":22},"试验设计",{"key":28,"text":247,"correct":22},"质量成本",{"key":31,"text":249,"correct":26},"基准分析",{"id":251,"libraryId":5,"type":15,"typeLabel":16,"stem":252,"options":253,"answer":20,"analysis":33},388375,"质量管理实施阶段的工具与技术不包括（ ）",[254,256,258,260],{"key":20,"text":255,"correct":26},"储备分析",{"key":24,"text":257,"correct":22},"统计抽样",{"key":28,"text":259,"correct":22},"过程决策程序图",{"key":31,"text":261,"correct":22},"质量审计",{"id":263,"libraryId":5,"type":15,"typeLabel":16,"stem":264,"options":265,"answer":28,"analysis":33},388376,"ISO9000标准提供（ ）",[266,268,270,272],{"key":20,"text":267,"correct":22},"关于如何生产产品的描述",{"key":24,"text":269,"correct":22},"执行质量系统的细节",{"key":28,"text":271,"correct":26},"质量系统的框架",{"key":31,"text":273,"correct":22},"保证客户得到好产品所必须的最大化需求",{"id":275,"libraryId":5,"type":15,"typeLabel":16,"stem":276,"options":277,"answer":24,"analysis":33},388377,"甲软件系统每年因故障中断10次，每次恢复平均要20分钟，乙软件系统每年因故障中断2次，每次恢复平均要5个小时。根据《软件工程产品质量GB\u002FT16260-2006》中可靠性和有有效性（或可用性）的定义，下面说法正确的是（ ）。",[278,280,282,284],{"key":20,"text":279,"correct":22},"甲系统的可靠性比乙系统高，可用性比乙系统差",{"key":24,"text":281,"correct":26},"甲系统的可用性比乙系统高，可靠性比乙系统差",{"key":28,"text":283,"correct":22},"甲系统的可靠性比乙系统高，可用性比乙系统高",{"key":31,"text":285,"correct":22},"甲系统的可靠性比乙系统差，可用性比乙系统差",{"id":287,"libraryId":5,"type":15,"typeLabel":16,"stem":288,"options":289,"answer":20,"analysis":33},388378,"应用Paretol图可以（ ）",[290,292,294,296],{"key":20,"text":291,"correct":26},"将精力集中到最关键的因素上",{"key":24,"text":293,"correct":22},"量化风险",{"key":28,"text":295,"correct":22},"帮助预测未来的问题",{"key":31,"text":297,"correct":22},"改进风险管理",{"id":299,"libraryId":5,"type":15,"typeLabel":16,"stem":300,"options":301,"answer":20,"analysis":33},388379,"规划质量管理的输入不包含（ ）。",[302,304,306,308],{"key":20,"text":303,"correct":26},"质量测量指标",{"key":24,"text":305,"correct":22},"项目管理计划",{"key":28,"text":307,"correct":22},"需求文件",{"key":31,"text":309,"correct":22},"风险登记册",{"id":311,"libraryId":5,"type":15,"typeLabel":16,"stem":312,"options":313,"answer":31,"analysis":33},388380,"质量管理计划描述下面所有的项，除了（ ）",[314,316,318,320],{"key":20,"text":315,"correct":22},"执行质量政策的方法",{"key":24,"text":317,"correct":22},"项目质量系统",{"key":28,"text":319,"correct":22},"执行项目质量管理所需要的组织结构、责任、程序、过程和资源",{"key":31,"text":321,"correct":26},"用于贯彻成本、进度和质量的平衡分析的程序",{"id":323,"libraryId":5,"type":15,"typeLabel":16,"stem":324,"options":325,"answer":31,"analysis":33},388381,"（ ）是编制质量规划的首要工作。",[326,328,330,332],{"key":20,"text":327,"correct":22},"需找影响质量的因素",{"key":24,"text":329,"correct":22},"研究项目产品说明书",{"key":28,"text":331,"correct":22},"确定质量度量指标",{"key":31,"text":333,"correct":26},"识别相关质量标准",{"id":335,"libraryId":5,"type":15,"typeLabel":16,"stem":336,"options":337,"answer":31,"analysis":33},388382,"（ ）可以作为项目质量控制中问题识别和问题分析的工具",[338,340,342,344],{"key":20,"text":339,"correct":22},"帕累托分析",{"key":24,"text":341,"correct":22},"直方图",{"key":28,"text":343,"correct":22},"核对表",{"key":31,"text":345,"correct":26},"因果分析",{"id":347,"libraryId":5,"type":15,"typeLabel":16,"stem":348,"options":349,"answer":28,"analysis":33},388383,"在某操作系统中，47%的错误是由该系统4%的程序模块产生的，该现象是（ ）特征。",[350,352,354,356],{"key":20,"text":351,"correct":22},"蒙特卡洛",{"key":24,"text":353,"correct":22},"大数定律",{"key":28,"text":355,"correct":26},"帕累托定律",{"key":31,"text":357,"correct":22},"PDPC",{"id":359,"libraryId":5,"type":15,"typeLabel":16,"stem":360,"options":361,"answer":31,"analysis":33},388384,"确定使用于项目的质量标准并决定如何满足这些标准是（ ）过程的主要功能。",[362,364,366,368],{"key":20,"text":363,"correct":22},"质量目标",{"key":24,"text":365,"correct":22},"质量保证",{"key":28,"text":367,"correct":22},"质量方针",{"key":31,"text":369,"correct":26},"质量计划",{"id":371,"libraryId":5,"type":15,"typeLabel":16,"stem":372,"options":373,"answer":31,"analysis":33},388385,"基于你的制造项目的质量控制测量，管理层认训到需要立即对材料需求计划（MRP）系统进行纠正，以避免在未来的项目中出现返工问题。为执行必要的变更，你必须遵循（ ）",[374,376,378,380],{"key":20,"text":375,"correct":22},"机构的质量政策",{"key":24,"text":377,"correct":22},"质量管理计划",{"key":28,"text":379,"correct":22},"已制订的操作定义和程序",{"key":31,"text":381,"correct":26},"整体变更控制程序",{"id":383,"libraryId":5,"type":15,"typeLabel":16,"stem":384,"options":385,"answer":31,"analysis":33},388386,"规划质量管理的过程中可以用到多种工具和技术。（ ）是一种统计方法，用来识别那些因素会对正在生产的产品或正在开发的流程的特定变量产生影响。",[386,388,390,392],{"key":20,"text":387,"correct":22},"成本效益分析法",{"key":24,"text":389,"correct":22},"质量成本法",{"key":28,"text":391,"correct":22},"标杆对照",{"key":31,"text":393,"correct":26},"实验设计",{"id":395,"libraryId":5,"type":15,"typeLabel":16,"stem":396,"options":397,"answer":20,"analysis":33},388387,"质量似乎是你们公司的追求。首先，公司通过了ISO9000认证。现在执行总裁想赢得MalcolmBaldrige奖。每个项目都有一份与机构的远景目标一致的质量综述。对所有项目提供内部和外部的质量保证以便（ ）",[398,400,402,404],{"key":20,"text":399,"correct":26},"确保项目满足相关的质量标准",{"key":24,"text":401,"correct":22},"监控特定的项目结果以确定它们是否符合相关的质量标准",{"key":28,"text":403,"correct":22},"找出排除不满意结果产生过程的方法",{"key":31,"text":405,"correct":22},"检查以排除过程中的错误",{"id":407,"libraryId":5,"type":15,"typeLabel":16,"stem":408,"options":409,"answer":28,"analysis":33},388388,"以下关于软件质量管理过程的叙述中，不正确的是（ ）。",[410,412,414,416],{"key":20,"text":411,"correct":22},"验证过程的目的是确保活动的输出产品满足活动的规范说明",{"key":24,"text":413,"correct":22},"确认过程的目的是确保产品满足其特定的目标",{"key":28,"text":415,"correct":26},"技术评审的目的之一是评价所用管理方法的有效性",{"key":31,"text":417,"correct":22},"审计是正式组织的活动",{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":28,"analysis":33},388389,"（ ）技术是确定为了完成项目工作所需的资源和技能水平的最佳方法。",[422,424,426,428],{"key":20,"text":423,"correct":22},"预测",{"key":24,"text":425,"correct":22},"挣值",{"key":28,"text":427,"correct":26},"专家判断",{"key":31,"text":429,"correct":22},"帕累托图",{"id":431,"libraryId":5,"type":15,"typeLabel":16,"stem":432,"options":433,"answer":28,"analysis":33},388390,"制定质量管理计划的主要依据是质量方针、项目范围说明书、产品描述以及（ ）。",[434,436,438,440],{"key":20,"text":435,"correct":22},"质量检查表",{"key":24,"text":437,"correct":22},"过程改进计划",{"key":28,"text":439,"correct":26},"质量标准与规则",{"key":31,"text":441,"correct":22},"需求变更请求",{"id":443,"libraryId":5,"type":15,"typeLabel":16,"stem":444,"options":445,"answer":31,"analysis":33},388391,"一个项目经理和他的团队正在使用鱼骨图（Ishikawa图）讨论所发现的一个重大质量问题的原因，这属于质量管理中的（ ）",[446,448,450,451],{"key":20,"text":447,"correct":22},"质量计划编制",{"key":24,"text":449,"correct":22},"质量工具",{"key":28,"text":365,"correct":22},{"key":31,"text":452,"correct":26},"质量控制",{"id":454,"libraryId":5,"type":15,"typeLabel":16,"stem":455,"options":456,"answer":28,"analysis":33},388392,"排列图（帕累托图）可以用来进行质量控制是因为（ ）。",[457,459,461,463],{"key":20,"text":458,"correct":22},"它按缺陷的数量多少画出一条曲线，反映了缺陷的变化趋势",{"key":24,"text":460,"correct":22},"它将缺陷数量从大到小进行了排列，使人们关注数量最多的缺陷",{"key":28,"text":462,"correct":26},"它引起缺陷的原因从大到小排列，项目团队应关注造成最多缺陷的原因",{"key":31,"text":464,"correct":22},"它反映了按时间顺序抽取的样本的数值点，能够清晰地看出过程实现的状态",{"id":466,"libraryId":5,"type":15,"typeLabel":16,"stem":467,"options":468,"answer":24,"analysis":33},388393,"组建团队是指获得人力资源的过程，项目管理团队应确保所选择的人力资源可以达到项目的要求。在此要求下，组建项目团队需要的输入应包括（ ）。①角色和责任②资源日历③项目的组织结构图④环境和组织因素⑤项目人员分配",[469,471,473,475],{"key":20,"text":470,"correct":22},"①②③",{"key":24,"text":472,"correct":26},"①③④",{"key":28,"text":474,"correct":22},"②③⑤",{"key":31,"text":476,"correct":22},"③④⑤",{"id":478,"libraryId":5,"type":15,"typeLabel":16,"stem":479,"options":480,"answer":28,"analysis":33},388394,"在组建项目团队时，人力资源要满足项目要求。以下说法，（ ）是不妥当的。",[481,483,485,487],{"key":20,"text":482,"correct":22},"对关键岗位要有技能标准，人员达标后方可聘用",{"key":24,"text":484,"correct":22},"与技能标准有差距的员工进行培训，合格后可聘用",{"key":28,"text":486,"correct":26},"只要项目经理对团队成员认可就可以",{"key":31,"text":488,"correct":22},"在组建团队时要考虑能力、经验、兴趣、成本等人员因素",{"id":490,"libraryId":5,"type":15,"typeLabel":16,"stem":491,"options":492,"answer":20,"analysis":33},388395,"对团队成员的激励永远是困扰项目经理的一个问题，对于高创新要求的项目团队来说，利用（ ）相对会更加有效。",[493,495,497,499],{"key":20,"text":494,"correct":26},"赋予更大的责任和权力",{"key":24,"text":496,"correct":22},"大幅增加薪酬",{"key":28,"text":498,"correct":22},"给予必要的关心和照顾",{"key":31,"text":500,"correct":22},"给予更高的社会地位",{"id":502,"libraryId":5,"type":15,"typeLabel":16,"stem":503,"options":504,"answer":28,"analysis":33},388396,"以下哪一项是项目小组建设的基本原则（ ）",[505,507,509,511],{"key":20,"text":506,"correct":22},"进行经常性的绩效评估",{"key":24,"text":508,"correct":22},"保证每个团队成员向他的职能经理和项目经理报告工作",{"key":28,"text":510,"correct":26},"尽早开始团队建设",{"key":31,"text":512,"correct":22},"尽力解决团队的政治问题",{"id":514,"libraryId":5,"type":15,"typeLabel":16,"stem":515,"options":516,"answer":31,"analysis":33},388397,"建设项目团队过程所使用的技术不包括（ ）。",[517,519,521,523],{"key":20,"text":518,"correct":22},"人际关系技能",{"key":24,"text":520,"correct":22},"基本规则",{"key":28,"text":522,"correct":22},"人事评测工具",{"key":31,"text":524,"correct":26},"项目人员分派",{"id":526,"libraryId":5,"type":15,"typeLabel":16,"stem":527,"options":528,"answer":24,"analysis":33},388398,"在某软件开发项目中，项目经理发现年轻开发人员流动的流失较为严重，导致项目进行中花费大量时间进行招聘、任务交接和善后处理。下列选项中无法改善人员流失状况的是（ ）。",[529,531,533,535],{"key":20,"text":530,"correct":22},"通过了解项目团员的感情，预测其行动，了解其后顾之忧，并尽力帮助他们解决问题",{"key":24,"text":532,"correct":26},"为了项目的完成，考虑到有限的人力资源，将该项目分包，在时限内完成项目",{"key":28,"text":534,"correct":22},"拨出专门团队建设经费，并鼓励团队内非正式的沟通和活动",{"key":31,"text":536,"correct":22},"建立培训和知识共享机制，使得所有的团队成员都可以学习到新的知识以及能够互相帮助",{"id":538,"libraryId":5,"type":15,"typeLabel":16,"stem":539,"options":540,"answer":20,"analysis":33},388399,"在冲突管理中，经常要集合多方观点和意见，得出一个多数人接受和承诺的冲突解决方案。这种冲突管理的方法被称为（ ）。",[541,543,545,547],{"key":20,"text":542,"correct":26},"合作",{"key":24,"text":544,"correct":22},"强制",{"key":28,"text":546,"correct":22},"妥协",{"key":31,"text":548,"correct":22},"回避",{"id":550,"libraryId":5,"type":15,"typeLabel":16,"stem":551,"options":552,"answer":24,"analysis":33},388400,"项目团队建设活动的首要目的是提高团队绩效，而很多活动所产生的附属效应也能够提高团队绩效。以下活动中，（ ）就代表了这种情况。",[553,555,557,559],{"key":20,"text":554,"correct":22},"建立一套以团队为基础的奖励与表彰系统",{"key":24,"text":556,"correct":26},"让非管理层的团队成员参与到项目计划制订过程中",{"key":28,"text":558,"correct":22},"确定团队绩效的目标，并审查达到这些目标的最佳方法",{"key":31,"text":560,"correct":22},"为所有团队成员安排一间大办公室进行集中工作",{"id":562,"libraryId":5,"type":15,"typeLabel":16,"stem":563,"options":564,"answer":24,"analysis":33},388401,"项目人力资源管理计划一般不包括（ ）",[565,567,569,571],{"key":20,"text":566,"correct":22},"项目中的角色和职责",{"key":24,"text":568,"correct":26},"绩效报告",{"key":28,"text":570,"correct":22},"项目组织结构图",{"key":31,"text":572,"correct":22},"人员配备管理计划",{"id":574,"libraryId":5,"type":15,"typeLabel":16,"stem":575,"options":576,"answer":28,"analysis":33},388402,"某项目团队每周组织羽毛球活动，根据马斯洛需求层次理论，该活动满足了项目成员（ ）的需求",[577,579,581,583],{"key":20,"text":578,"correct":22},"生理",{"key":24,"text":580,"correct":22},"受尊重",{"key":28,"text":582,"correct":26},"社会交往",{"key":31,"text":584,"correct":22},"自我实现",{"id":586,"libraryId":5,"type":15,"typeLabel":16,"stem":587,"options":588,"answer":31,"analysis":33},388403,"（ ）不能作为编制人力资源计划的工具",[589,591,593,595],{"key":20,"text":590,"correct":22},"层次结构图",{"key":24,"text":592,"correct":22},"责任分配矩阵",{"key":28,"text":594,"correct":22},"文本格式的角色描述",{"key":31,"text":596,"correct":26},"团队成员的通讯录",{"id":598,"libraryId":5,"type":15,"typeLabel":16,"stem":599,"options":600,"answer":20,"analysis":33},388404,"项目经理管理项目团队有时需要解决冲突，（ ）属于解决冲突的范畴。",[601,603,605,607],{"key":20,"text":602,"correct":26},"强制、妥协、撤退",{"key":24,"text":604,"correct":22},"强制、求同存异、观察",{"key":28,"text":606,"correct":22},"妥协、求同存异、增加权威",{"key":31,"text":608,"correct":22},"妥协、撤退、预防",{"id":610,"libraryId":5,"type":15,"typeLabel":16,"stem":611,"options":612,"answer":31,"analysis":33},388405,"关于项目管理环境中的冲突管理的叙述中，_（ ）是正确的。",[613,615,617,619],{"key":20,"text":614,"correct":22},"通过建立团队基本规则及实施可行的项目管理经验，冲突是可以避免的",{"key":24,"text":616,"correct":22},"解决冲突最理想方法是求同存异",{"key":28,"text":618,"correct":22},"冲突管理的最终目的是消除意见分歧",{"key":31,"text":620,"correct":26},"不管冲突对项目的影响是正面的还是负面的，项目里都有责任处理它",[622,626,629,632,635,638],{"id":623,"name":624,"category":7,"favorite":625},136,"法律职业试卷二(客观题 )",2,{"id":627,"name":628,"category":7,"favorite":15},137,"法律职业试卷一(客观题 )",{"id":630,"name":631,"category":7,"favorite":15},176,"（初级）社会工作实务",{"id":633,"name":634,"category":7,"favorite":15},177,"（初级）社会综合能力",{"id":636,"name":637,"category":7,"favorite":8},28,"安全工程师",{"id":639,"name":640,"category":7,"favorite":8},112,"安全生产法律知识"]