[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-172-38":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":94},{"id":5,"name":6,"category":7,"favorite":8},172,"(高级)信息系统项目管理师","职业资格",0,38,50,1856,[13,34,46,58,70,82],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":20,"analysis":33},390079,1,"单选题","决策树分析是风险分析过程中的一项常用技术。某企业在项目风险分析过程中，采用了决策树分析方法，并计算出了EMV（期望货币值）。以下说法中，正确的是 （ ） 。",[19,23,27,30],{"key":20,"text":21,"correct":22},"A","以上进行的是定量风险分析，根据分析结果应选择修改现有技术方案的路线",true,{"key":24,"text":25,"correct":26},"B","以上进行的是定量风险分析，根据分析结果应选择设计新技术方案的路线",false,{"key":28,"text":29,"correct":26},"C","以上进行的是定性风险分析，根据分析结果应选择修改现有技术方案的路线",{"key":31,"text":32,"correct":26},"D","以上进行的是定性风险分析，根据分析结果应选择设计新技术方案的路线","",{"id":35,"libraryId":5,"type":15,"typeLabel":16,"stem":36,"options":37,"answer":20,"analysis":33},390080,"确定哪些风险会影响项目并记录风险的特性，这个过程称为 （ ） 。",[38,40,42,44],{"key":20,"text":39,"correct":22},"风险识别",{"key":24,"text":41,"correct":26},"风险处理",{"key":28,"text":43,"correct":26},"经验教训学习",{"key":31,"text":45,"correct":26},"风险分析",{"id":47,"libraryId":5,"type":15,"typeLabel":16,"stem":48,"options":49,"answer":31,"analysis":33},390081,"下面 （ ）不是风险审计的目标。",[50,52,54,56],{"key":20,"text":51,"correct":26},"确定风险管理已经在项目的整个生命周期中实施",{"key":24,"text":53,"correct":26},"确定项目被管理好，风险被控制",{"key":28,"text":55,"correct":26},"协助在早期阶段鉴别项目的价值潜力的退化",{"key":31,"text":57,"correct":22},"确保被识别的和相当有威胁的每一个风险都有计算的预期值",{"id":59,"libraryId":5,"type":15,"typeLabel":16,"stem":60,"options":61,"answer":31,"analysis":33},390082,"某系统集成企业为做好项目风险管理，给风险定义了3个参数。（1）风险严重性：指风险对项目造成的危害程度；（2）风险可能性：指风险发生的几率；（3）风险系数：是风险严重性和风险可能性的乘积。其中，对项目进度延误、费用超支的风险严重性等级和风险可能性等级如下表所示。 假定该企业将风险系数大于等于10的情况定义为红灯状态，需要优先处理，则下列（ ） 的情况属于红灯状态。",[62,64,66,68],{"key":20,"text":63,"correct":26},"进度延误15%，费用超支15%，发生几率为0.5",{"key":24,"text":65,"correct":26},"进度延误15%，费用超支35%，发生几率为0.2",{"key":28,"text":67,"correct":26},"进度延误15%，费用超支25%，发生几率为0.3",{"key":31,"text":69,"correct":22},"进度延误25%，费用超支15%，发生几率为0.4",{"id":71,"libraryId":5,"type":15,"typeLabel":16,"stem":72,"options":73,"answer":24,"analysis":33},390083,"在处理已识别的风险及其根源时，______用来检查并记录风险应对策略的效果以及风险管理过程的效果。",[74,76,78,80],{"key":20,"text":75,"correct":26},"风险再评估",{"key":24,"text":77,"correct":22},"风险审计",{"key":28,"text":79,"correct":26},"预留管理",{"key":31,"text":81,"correct":26},"偏差和趋势分析",{"id":83,"libraryId":5,"type":15,"typeLabel":16,"stem":84,"options":85,"answer":24,"analysis":33},390084,"德尔菲法区别于其他专家预测法的明显特点是（）。",[86,88,90,92],{"key":20,"text":87,"correct":26},"引入了权重参数",{"key":24,"text":89,"correct":22},"多次有控制的反馈",{"key":28,"text":91,"correct":26},"专家之间互相取长补短",{"key":31,"text":93,"correct":26},"至少经过4轮预测",[95,99,102,105,108,111],{"id":96,"name":97,"category":7,"favorite":98},136,"法律职业试卷二(客观题 )",2,{"id":100,"name":101,"category":7,"favorite":15},137,"法律职业试卷一(客观题 )",{"id":103,"name":104,"category":7,"favorite":15},176,"（初级）社会工作实务",{"id":106,"name":107,"category":7,"favorite":15},177,"（初级）社会综合能力",{"id":109,"name":110,"category":7,"favorite":8},28,"安全工程师",{"id":112,"name":113,"category":7,"favorite":8},112,"安全生产法律知识"]