[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390081":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},390081,172,1,"单选题","下面 （ ）不是风险审计的目标。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","确定风险管理已经在项目的整个生命周期中实施",false,{"key":16,"text":17,"correct":14},"B","确定项目被管理好，风险被控制",{"key":19,"text":20,"correct":14},"C","协助在早期阶段鉴别项目的价值潜力的退化",{"key":22,"text":23,"correct":24},"D","确保被识别的和相当有威胁的每一个风险都有计算的预期值",true,"风险审计的目标有：确定风险管理已经在项目的整个生命周期中实施，确定项目被管理好，风险被控制，协助在早期阶段鉴别项目的价值潜力的退化等。“确保被识别的和相当有威胁的每一个风险都有计算的预期值”是没有必要的，因为对发生概率小、影响小的风险就无需去定量计算，所以审计也就没有必要。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]