[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390066":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},390066,172,1,"单选题","项目经理在6月1日对一个软件开发项目进行了挣值分析，项目CPI是1.0，进度偏差是0，在6月3日，附近的河流泛滥，致使开发计算机机房被淹，导致所有工作停工两周时间。该项目遭受了 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","已知的可预测风险",false,{"key":16,"text":17,"correct":18},"B","已知的不可预测风险",true,{"key":20,"text":21,"correct":14},"C","未知的可预测风险",{"key":23,"text":24,"correct":14},"D","未知的不可预测风险","这是已知的未知风险，在河流边上，就应该预计到可能有河流泛滥，同样的场景还有暴风雨肆掠的地区或季节发生暴风雨、地震频发地区发生地震等。未知的未知就是没有任何征兆会发生但是突然发生了。河流会发生洪水这是已知的，但是什么时候发生又是不可预测的，所以是已知的不可预测风险。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]