[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},390064,172,1,"单选题","项目风险识别是指找出影响项目目标顺利实现的主要风险因素，并识别出这些风险究竟有哪些基本特征、可能会影响到项目的哪些方面等问题。以下关于项目风险识别的叙述中，正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","主要由项目经理负责项目风险识别活动",false,{"key":16,"text":17,"correct":18},"B","风险识别是一种系统活动，而不是一次性行为",true,{"key":20,"text":21,"correct":14},"C","主要识别项目的内在风险",{"key":23,"text":24,"correct":14},"D","风险识别包括外在因素对项目本身可能造成的影响评估","影响评估是定性风险分析。风险识别需要全员全过程参与，要识别内部和外部风险。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]