[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},390063,172,1,"单选题","项目经理在某项目实施阶段的中期发现，由于未预料到的变更，项目经费要花光了，此时应 （ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对项目进行赶工或快速跟进",false,{"key":16,"text":17,"correct":18},"B","重新评估风险分析结果和应急资金",true,{"key":20,"text":21,"correct":14},"C","要求对项目预算做变更",{"key":23,"text":24,"correct":14},"D","使用不对项目收费的资源","选项A和C并不能解决潜在的问题，选项D缺乏职业道德。重新评估风险分析结果和应急资金，既考虑了现在遇到的问题，又对未来重新进行了调研，所以正确答案为选项B。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]