[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390062":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},390062,172,1,"单选题","（ ）不属于风险管理计划编制的成果。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险类别",false,{"key":16,"text":17,"correct":14},"B","风险概率",{"key":19,"text":20,"correct":14},"C","风险影响力的定义",{"key":22,"text":23,"correct":24},"D","风险记录",true,"风险管理计划包括:①方法论、②角色和职责、③预算、④制订时间表、⑤风险类别、⑥风险概率和影响力的定义、⑦概率及影响矩阵、⑧已修订的项目干系人对风险的容忍度⑨报告的格式、回跟踪",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]