[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390041":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},390041,172,1,"单选题","某系统集成企业迫于经营的压力，承接了一个极具技术风险的项目，该项目的项目经理为此：调用了公司最有能力的人力资源，组织项目组核心团队成员培训，与该项目技术领域最强的研究团队签订项目技术分包协议，从项目风险管理的角度来看，该项目经理采取了（ ） 的应对策略。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应急分享",false,{"key":16,"text":17,"correct":18},"B","正向风险",true,{"key":20,"text":21,"correct":14},"C","转移风险",{"key":23,"text":24,"correct":14},"D","负面风险","迫于经营的压力，这个风险项目其实已经是一个机会了，不接这个项目公司就倒闭了，所以什么风险都不是风险啦。这个极具风险的项目有可能给这个企业带来利益，因此总的来说是个正向风险，所以选B。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]