[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390038":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},390038,172,1,"单选题","某项目经理刚刚完成了项目的风险应对计划， （ ） 应该是风险管理的下一步措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定项目整体风险的等级",false,{"key":16,"text":17,"correct":14},"B","开始分析那些在产品文档中发现的风险",{"key":19,"text":20,"correct":21},"C","在工作分解结构上增加任务",true,{"key":23,"text":24,"correct":14},"D","进行风险审核","风险应对计划完成后一经认可，风险记录的更新也要落实到项目的WBS中（如把风险的监控与应对作为新任务增加到WBS中），还要对项目管理计划进行更新，用更新的计划来指导和管理项目的执行。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]