[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},390034,172,1,"单选题","下列工程项目风险事件中， （ ） 属于技术性风险因素。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","新材料供货不足",false,{"key":16,"text":17,"correct":18},"B","设计时未考虑施工要求",true,{"key":20,"text":21,"correct":14},"C","索赔管理不力",{"key":23,"text":24,"correct":14},"D","合同条款表达有歧义","为了深入、全面地认识项目风险，并有针对性地进行管理，有必要将风险分类。其中技术性风险因素包括项目的技术、质量和性能方法等方面可能存在的风险。“新材料供货不足”属于外部风险的“市场风险”。“设计时未考虑施工要求”属于技术风险中的“技术风险”。“索赔管理不力”属于“外部的”风险中的“法律”风险。“合同条款表达有歧义”属于“外部的”风险中的“客户”风险。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]