[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},390028,172,1,"单选题","以下关于IT项目风险应对策略的描述中， （ ） 是错误的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","策略必须具有时效性",false,{"key":16,"text":17,"correct":14},"B","策略必须与风险的严重程度相一致，避免花费比风险后果更多的资源去预防风险",{"key":19,"text":20,"correct":14},"C","对于某个比较重要的风险，可以采用单个风险应对计划表来对其进行管理",{"key":22,"text":23,"correct":24},"D","为避免风险进一步扩大，尽可能让更少的项目干系人参与",true,"不能闭门造车，要让相关的干系人一起参与。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]