[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390027":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},390027,172,1,"单选题","由于大型项目团队构成复杂，因此在制订风险管理计划时，首先要考虑 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织及参与项目的人员的风险态度和风险承受度",true,{"key":16,"text":17,"correct":18},"B","已识别风险清单",false,{"key":20,"text":21,"correct":18},"C","项目风险的相对排序或优先度清单",{"key":23,"text":24,"correct":18},"D","风险的应对策略","选项B是识别风险的输出。选项C是定性风险的输出。选项D是规划应对的输出。所以，正确选项是A。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]