[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},390020,172,1,"单选题","主要风险清单是常用的项目风险管理工具，如下图所示。以下关于风险清单的叙述中，（ ）是不正确的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","该风险清单应在需求分析之前建立，并在项目结束前不断定期维护",false,{"key":16,"text":17,"correct":14},"B","项目经理、风险管理贵任人应每隔一周左右回顾该风险清单",{"key":19,"text":20,"correct":21},"C","应该对风险清单中的部分主要风险制定详细的风险应对计划",true,{"key":23,"text":24,"correct":14},"D","对风险清单的回顾应包含在进度计划表中，否则可能被遗忘","在风险清单中列出的风险并不一定会对项目造成影响，需要经过定量和定性分析后才进行风险应对。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]