[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-390016":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},390016,172,1,"单选题","某通信设备采购项目，签订合同后进入了合同履行阶段，以下 （ ） 做法是不合理的。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同履行过程中发现处于支付的通信设备的质量及验收要求约定不明确，双方进行商议后以补充协议进行了规定",false,{"key":16,"text":17,"correct":14},"B","由于采购方不具备接收通信设备的条件，要求供货方延迟货物的交付，到了实际交付时，由于该通信设备的价格涨价，供货方要求变更合同价格",{"key":19,"text":20,"correct":21},"C","通信设备在运输至采购方的过程中，遇到了连续的暴雨天气无法按时交付，采购方认为合同中没有对应的免责条款，对供货方进行经济索赔",true,{"key":23,"text":24,"correct":14},"D","合同双方在履行过程中产生了纠纷，双方无法协调一致，因此向仲裁机构提出了仲裁申请。","“连续的暴雨天气”，并且是在运输途中，寓意是“事先无法通过天气预报或每年的气候惯例预先做出妥善安排”，这属于不可抗力；合同中尽管无免责条款，但也要考虑市场惯例。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]