[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389994":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389994,172,1,"单选题","某系统集成商中标一个县政府办公系统的开发项目，该项目在招标时己经明确确定该项目的经费不超过150万元，此项目适合签订（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工料合同",false,{"key":16,"text":17,"correct":14},"B","成本补偿合同",{"key":19,"text":20,"correct":14},"C","分包合同",{"key":22,"text":23,"correct":24},"D","总价合同",true,"根据《系统集成项目管理工程师教程（第2版）》第446页，1．总价合同 总价合同又称固定价格合同，是指在合同中确定一个完成项目的总价，承包人据此完成项目全部合同内容的合同。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]