[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389990":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389990,172,1,"单选题","某项目经理要求采购管理员从外面供货商那里采购硬件设备时，需要准备一个 （ ） 以描述采购设备的相关质量技术指标，验收标准和付款方式与期限等内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工作说明书",true,{"key":16,"text":17,"correct":18},"B","合同范围说明",false,{"key":20,"text":21,"correct":18},"C","项目章程",{"key":23,"text":24,"correct":18},"D","合同","采购工作说明书中的信息有规格说明书、期望的数量和质量的等级、性能数据、履约期限、工作地以及其他要求",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]