[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389985,172,1,"单选题","以下关于采购工作说明书的叙述中， （ ） 是错误的。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购说明书与项目范围基准没有关系",true,{"key":16,"text":17,"correct":18},"B","采购工作说明书与项目的工作说明书不同",false,{"key":20,"text":21,"correct":18},"C","应在编制采购计划的过程中编写采购工作说明书",{"key":23,"text":24,"correct":18},"D","采购工作说明书定义了与项目合同相关的范围","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]