[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389978":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389978,172,1,"单选题","（ ） 涉及到结算和关闭项目所建立的任何合同、采购或买进协议，也定义了为支持项目的正式收尾所需的相关合同的活动。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","行政收尾",false,{"key":16,"text":17,"correct":18},"B","合同收尾",true,{"key":20,"text":21,"correct":14},"C","变更收尾",{"key":23,"text":24,"correct":14},"D","管理收尾","合同收尾是把项目上的每个合同都了结，包括工作完成、产品验收和移交、价款结算和争议解决等。行政收尾是指对项目工作进行全面、系统和深入的回顾，进行完工后评价，考察“如果有机会重新做该项目可以如何改进”，把有关经验教训提炼出来并形成文档，并使它成为“组织过程资产”的一部分。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]