[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389972":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389972,172,1,"单选题","在建设工程合同的订立过程中，投标人根据招标内容在约定期限内向招标人提交的投标文件，此为（ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","要约邀请",false,{"key":16,"text":17,"correct":18},"B","要约",true,{"key":20,"text":21,"correct":14},"C","承诺",{"key":23,"text":24,"correct":14},"D","承诺生效","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]