[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389967,172,1,"单选题","关于信息工程实施合同中关于工期的叙述，不正确的是 ______。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在合同协议书内应明确注明开工日期",false,{"key":16,"text":17,"correct":14},"B","在合同协议书内应明确注明竣工日期",{"key":19,"text":20,"correct":14},"C","在合同协议书内应明确注明合同工期总日历天数",{"key":22,"text":23,"correct":24},"D","通过招标选择承包人的项目，其合同工期天数就是招标文件要求的工期天数",true,"在4个选项中，因履行期限如开工日期、竣工日期等都是合同的构成要件，因此选项A、B、C是正确的。因工期以合同规定为准，因此选项D是不正确的。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]