[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389962":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},389962,172,1,"单选题","某公司按总价格合同方式约定订购3000米高规格的铜缆，由于建设单位原因，工期暂停了半个月，待恢复施工后，承建单位以近期铜价上涨为理由，要求建设单位赔偿购买电缆增加的费用，并要求适当延长工期，以下说法中， （ ） 是正确的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位应该赔偿承建单位采购电缆增加的费用",false,{"key":16,"text":17,"correct":14},"B","监理单位应该保护承建单位的合法利益，因此应该支持承建的索赔要求",{"key":19,"text":20,"correct":14},"C","索赔是合同双方利益的体现，可以使造价更趋于合理",{"key":22,"text":23,"correct":24},"D","铜价上涨是承建单位应承担的项目风险，不应该要求赔偿费用",true,"总价格合同属于闭口合同，工作量不变，则总价不变；工作量变动，则总价变动。而铜价上涨属于承建单位应该自身承担的风险，建设方不予赔偿。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]