[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389958":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389958,172,1,"单选题","某项工程需在室外进行线缆铺设，但由于连续大雨造成承建方一直无法施工，开工日期比计划晚了2周（合同约定持续1周以内的天气异常不属于反常天气），给承建方造成一定的经济损失。承建方若寻求补偿，应当 （ ） 。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","要求延长工期补偿",true,{"key":16,"text":17,"correct":18},"B","要求费用补偿",false,{"key":20,"text":21,"correct":18},"C","要求延长工期补偿、费用补偿",{"key":23,"text":24,"correct":18},"D","自己克服","",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]