[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389955":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},389955,172,1,"单选题","项目发生索赔事件后，一般先由 （ ） 依据合同进行调解。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","政府行政主管部门",false,{"key":16,"text":17,"correct":18},"B","监理工程师",true,{"key":20,"text":21,"correct":14},"C","仲裁委员会",{"key":23,"text":24,"correct":14},"D","项目经理","本题考核索赔的程序。项目发生索赔事件后，一般先由监理工程师调解，若调解不成，由政府建设主管机构进行调解，若仍调解不成，由经济合同仲裁委员会进行调解或仲裁。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]