[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389954":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},389954,172,1,"单选题","信息系统设备供应商在与业主单位签订采购合同前，因工期要求，已提前将所采购设备交付给业主单位，并通过验收。补签订合同时，合同的生效日期应当为（29）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","交付日期",true,{"key":16,"text":17,"correct":18},"B","委托采购日期",false,{"key":20,"text":21,"correct":18},"C","验收日期",{"key":23,"text":24,"correct":18},"D","合同实际签订日期","依据《合同法》第三十七条规定，“采用合同书形式订立合同，在签字或者盖章之前，当事人一方已经履行主要义务，对方接受的，该合同成立。”第二十五条规定，“承诺生效时合同成立。”第二十六条规定，“承诺通知到达要约人时生效。”",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]