[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-389953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},389953,172,1,"单选题","乙公司中标承接了甲机构的网络工程集成项目，在合同中约定了因不可抗力因素导致工期延误免责的条款，其中不会被甲机构认可的不可抗力因素是 （28） 合同约定， 。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工现场遭遇长时间雷雨天气",false,{"key":16,"text":17,"correct":14},"B","物流公司车辆遭遇车祸",{"key":19,"text":20,"correct":21},"C","乙方施工队领导遭遇意外情况",true,{"key":23,"text":24,"correct":14},"D","施工现场长时间停电","不可抗力因素是指自然、环境或者不可控制的第三方因素，乙方自身的因素一般不算在不可控制第三方因素的范围之内。",{"id":6,"name":27,"category":28,"favorite":29},"(高级)信息系统项目管理师","职业资格",0]